Use Case: Energy Optimization at Getec with Top-Energy

Innovative Energy Supply Concepts for a Climate-Friendly Industry

GETEC is Europe’s leading specialist in reliable, decarbonized energy and infrastructure solutions. With more than 3,100 dedicated employees at approximately 50 locations, GETEC applies its expertise in technology, regulation, and sustainability to serve its industrial and real estate clients. In this way, GETEC helps them navigate the complex landscape of the modern energy market while significantly reducing their carbon footprint. With over 11,000 facilities, the company offers a broad range of sustainable technologies. GETEC develops, finances, and operates critical energy infrastructure throughout Europe, including in Germany, Italy, Switzerland, the Benelux countries, Austria, and Poland.

Challenge: Designing Complex Energy Systems to Be Economical and Sustainable

The energy transition poses a growing challenge, particularly for industrial companies. Increasing regulatory requirements, a growing share of renewable energy in the power grid, and a changing electricity market structure are leading to greater complexity in the energy supply sector. In this environment, the integration of electricity and heat is becoming increasingly important for implementing energy systems with the lowest possible CO₂ emissions.

GETEC plans, finances, builds, and operates decentralized, demand-driven generation facilities for industrial customers.

Case Study: Innovative Heat Pump System at the Hilchenbach Site

The SMS group’s Hilchenbach site serves as a successful example of the implementation of innovative energy concepts. Here, GETEC installed one of the largest air-to-water heat pump systems in Germany. The technology uses ambient heat to meet the annual heat demand of 12,000 MWh. Thanks to a two-stage configuration of the heat pumps combined with an electric boiler, the desired flow temperature of 95 °C can be achieved even at low outdoor temperatures.

The TOP-Energy Solution: Simulating and Optimizing Complex Energy Systems

To develop such modern, cross-sector energy concepts, high-temporal-resolution simulations are essential. The interplay between generation, consumption, and storage—taking energy markets into account—must be modeled realistically. This is where GETEC’s TOP-Energy software solution comes into play. The software supports the planning phase by simulating potential energy concepts while accounting for real-world constraints. This enables GETEC to make well-informed decisions regarding cost-effectiveness, efficiency, and sustainability, thereby identifying the optimal energy concept for each situation.

For the project at the Hilchenbach site of the SMS group, an optimal supply concept was developed on this basis, combining a heat pump and an electric boiler with a thermal storage tank. This decouples supply and demand and enables flexible operation as well as participation in energy markets. As a result, the system is able to respond to the volatility of renewable energy sources and provide balancing power for the transmission system operator.

The Result: 6,000 Metric Tons Less CO₂ per Year and Greater Flexibility

Overall, the system can reduce CO₂ emissions by approximately 6,000 metric tons per year. This makes the concept a significant step toward decarbonizing heat generation and achieving climate-neutral operations.

By taking into account the day-ahead electricity price and the balancing energy markets as early as the concept development phase, energy systems are created that are not only economically attractive to GETEC’s customers but also actively contribute to grid stability and the success of the energy transition. The combination of robust simulation and comprehensive economic feasibility analysis makes TOP-Energy a suitable tool for GETEC in developing sustainable, cross-sector energy concepts.